What inspections are required for my remodeling project?
Depending on your locality and it's unique requirements the following list may differ however the most common schedule for residential building inspections is as follows.
1. Open footings after excavation before pour
2. Spread footing poured with keyway or vertical steel or monolithic pour with no keyway required
3. Foundation forms in place
4. Foundation wall following pour
5. Electrical rough in following completion of framing
6. Plumbing rough in following completion of framing
7. Framing inspection with electrical and plumbing satisfied or during the framing inspection
8. Insulation
9. Some localities require a sheetrock "screw" pattern inspection
10. Final inspection following full completion of the project ready to move upon which a Certificate of Occupancy or CO is issued to you the homeowner.
Always check with your local building and safety authority as these requirements can change from time to time with little or no notice.